Slurry Schedule Updated

Due to unforeseen circumstances, all roads originally scheduled to be sealed on Monday were not able to be completed.  Estates Drive, Election Way, and American Way have been rescheduled for Saturday 7/17. We apologize for any inconvenience this may have caused.  07132021_MoveMo2021_SlurrySchedule

As a reminder, contractors will begin work each day at 7am. If your road is scheduled to be sealed and has "No Parking" signs along the road, please be prepared for the road to be closed until the slurry has cured. Should you need to leave your home after 7 am, please prepare for the closure and relocate your vehicle to a street that does not have "No Parking" signs prior to the start of the slurry seal process. The curing period typically takes 4-5 hours once placed. During this period cars will not be permitted to drive on the freshly placed slurry.  The updated construction schedule is as follows:

  • Wednesday 7/14: Biron Road, Meadows Parkway (between 6700 Rd and Sara E Lane), E Fox Park Street, Valley Way, Consitution Loop. 
  • Thursday 7/15: Sara E Lane, Natalia Way, Kia Lane (south of Meadows Pkwy), Mead Lane (between Meadows Pkwy and Patriot Ct) and Republic Avenue. 
  • Friday 7/16: Meadows Parkway (between 6700 Rd and Stan Dr), Patriot Court, Mead Lane (east of Patriot Ct), Cook Drive, and Hill Street (south of American Way).
  • Saturday 7/17:  Estates Drive, American Way, Election Way, Meadows Parkway (east of Stan Dr), and Hill Street (north of American Way). Final clean up and any rework areas.

Any questions regarding the project may be directed to Civil Engineer Ryan Cushenan at 970.240.1485 or rcushenan@ci.montrose.co.us. Please visit www.MoveMo.co for routine project updates and information on other large capital projects taking place throughout the city.

Facebook Twitter Email

Other News in Moving Montrose Forward News

Woodgate Realignment Paving Schedule

Posted on: September 20, 2021

Slurry Seal Schedule Announced

Posted on: July 1, 2021
06182021WoodgateRealignmentHouses

Woodgate Houses Moved

Posted on: June 18, 2021
Asphalt Patching

Asphalt Patching 5/3-7

Posted on: May 3, 2021
041621SunsetTank_003

Sunset Mesa Water Tank Going Vertical

Posted on: April 21, 2021

Sunset Mesa Tank Foundation Poured

Posted on: March 16, 2021