Beginning Monday, September 23rd, contractors working for the City will begin chip sealing roads previously patched and crack sealed earlier this summer. See below for the anticipated schedule. Roads will be reduced to a single lane of traffic controlled by flaggers during active construction.
The City asks motorists and pedestrians to please exercise caution throughout the work area and to please respect all coned off areas. Navigate to MoveMo.Co for more information and routine project updates.
Any questions regarding the project may be directed to Civil Engineer Ryan Cushenan at (970) 240-1485.
Sept 23rd Chip Seal: Locust Road and begin Sunnyside Road
Sept 24th Chip Seal: Finish Sunnyside and 6300 Road
Sept 24th-25th Sweep: Pick up brooming excess chips
Sept 26th Fog Seal: Locust Road, Sunnyside, and 6300 Road
Oct 3rd Painting: Locust Road, Sunnyside Road, and 6300 Road